Polaris
gets Customised Docking Blocks in Cape Town
There were a few options as to where the Stolt Offshore "Seaway
Polaris" thruster inspection and refit would take place. Cape Town
was a strong contender - but not without some interesting problems which
had to be solved first. The Cape Town Sturrock dry dock is owned and
operated by the National Port Authority, who do not engage in any ship
repair works, so the procedure for securing a position in the dry dock is
different to most other places in the world where the successful shipyard
would dock the vessel in their own dry dock.
The thruster removal procedure required the centreline block height of
the barge to be 3,8m. The Sturrock dock standard blocking line height in
the centre of the dock was 1,4m, and the National Port Authority would not
consider any other block height.
Anton
Wale & Associates were asked in March 2002 if they were prepared to
engineer - at risk - a solution for the increased blocking line, with the
understanding that if the vessel was going to be dry docked in Cape Town,
they would get to design & supply the blocking line.
By
15 March the first proposal was submitted, which employed a combination of
a 100 te SWL concrete base piece with the NPA standard blocks on top. This
was soon modified to a single 100 te SWL concrete column with cruciform
base and vessel bearing pad the same dimensions as the NPA.
After
many more hours of deliberation, the final design was submitted on 10
April 2002. This solution employed approximately 144 reinforced concrete
blocks, each with a SWL of 200 tonnes and a mass of approximately 8 tonnes
- as shown in the pictures above.
The fabrication time for blocks was 7 weeks.
|